Approaching crunch time on Liddell

The AFR reports that Alinta is finalising its bid for Liddell, energy minister Josh Frydenberg says by the end of April, so any day now. That was in response to the announcement by AGL the day before that it will build the 252-megawatt gas-fired plant near its Newcastle Gas Storage Facility, completing construction at the end of 2022, for the cost of $400 million:

Above is an artist impression of a similar facility in South Australia.

Frydenberg was not impressed. Continue reading Approaching crunch time on Liddell